Risk Identification Efficiency is the ratio of Number of Risk identified to sum of Number of Risk identified and Number of Risk occurred in a project. It determines the efficiency of identifying risk in a project. It helps in planning for the mitigation and contingency to be carried out in a project.
Risk Identification Efficiency is calculated at overall project level.
How to calculated Risk Identification Efficiency:
Risk Identification Efficiency % = (Total no. of Risks Identified) / (Total no. of Risks Identified + Total no. of Risk occurred) * 100
Total no. of Risks Identified
|
Total no. of Risk occurred
|
Risk Identification Efficiency %
|
9
|
6
|
60
|
Risk Identification Efficiency % = 9 / (9 + 6) *100
= 60 %