Test Effectiveness is the ratio of difference of Total no. of application defects found by test team and Total no. of application defects rejected by the customer/developer to sum of Total no. of application defects found by test team and Total no. of defects found by customer/test team during UAT.
Test Effectiveness metric is used to measure the test effectiveness of test team and is calculated at the end of test execution phase.
Test Effectiveness metric is used to measure the test effectiveness of test team and is calculated at the end of test execution phase.
How to calculate Test Effectiveness:
Test Effectiveness = (Total no. of application defects found by test team - Total no. of application defects rejected by the customer/developer) / (Total no. of application defects found by test team + Total no. of defects found by customer/test team during UAT) *100
Example:
Total no. of defects found by test team
|
Total no. of defects Rejected by Customer/Dev team
|
Total no. of defects found by customer/test team during UAT
|
Test Effectiveness
|
80
|
5
|
2
|
91.46
|
Test Effectiveness = (80-5) / (80+2) * 100
= 91.46 %